The GDNA, granted "party status", appeared on July 19th for a 10am start to the 4-day OMB hearing related to the "James" development at 452 Richmond Street West.
However, at the request of lawyers for the City and Brad Lamb, the hearing was rescheduled to May 29, 2017 for a duration of two full weeks ... 10 days, not just 4 ... This to accommodate the testimony and cross-examination of eight expert witnesses (four for the City, three for Brad Lamb's team and one for the GDNA). There will obviously be little in the way of updates for the next 9 months ... certainly nothing to suggest that anything will be "coming soon".